Garment Production Capacity Calculator
Plan a sewing line. From the number of operators, working hours, line efficiency and SAM (standard allowed minutes) of the garment, see how many pieces you can make.
Questions
What is SAM?
SAM is the standard allowed minutes to make one garment, found by adding the time of every operation plus allowances. A basic T-shirt is about 4 to 6 SAM and a shirt about 12 to 18 SAM.
How is output worked out?
Output per day = operators × hours × 60 × efficiency ÷ SAM. Operators needed = target × SAM ÷ (hours × 60 × efficiency).
What is a normal line efficiency?
New lines often start at 40 to 50 percent and settle at 60 to 75 percent. Very well run lines reach 80 percent or more on simple styles.